Fri 21 April 2006

Dad continued with grounding and layout work on the firewall.
After more thought, we took the plunge on the first large eyeball location. Hopefully this will be for the P2 prop control.
I continued with the avionics rack, drilling and tapping 3 locations each side.
Then the mock panel was drilling / recut for the avionics rack - some refinement needed for the upper cut. Also played with using a smaller cut out for the EIS4000 and flush mounting it from behind - I think it might work well.